Following is an excerpt from a report in Business Standard.

The first phase of the Naveen Jindal-promoted Jindal Steel and Power Ltd (JSPL)’s proposed 6 million tonne per annum (mtpa) steel project and 1000 Mw power plant at Angul in Orissa is expected to be commissioned in 2011-12.

The shifting of families to be displaced by the project was going on and simultaneously, the construction of the boundary wall had started. The detailed engineering would follow the completion of the rehabilitation and resettlement (R&R) of displaced persons and large scale construction would be taken up after that.

“We plan to start large scale construction work in January next year and the first phase commissioning is scheduled to be in 2011-12”, Rajesh Kumar Jha, executive director, JSPL told Business Standard.

He said, out of three villages to be shifted completely for the first phase construction, two villages had been rehabilitated completely. The remaining village would be rehabilitated by December this year. The company’s strategy of combining the project economy with the rehabilitated family’s economy has gone down well with the people. …

… the company had placed orders for civil and structural works worth Rs 1584.57 crore which was 60 percent of the estimated costs. Similarly, orders for plant and equipment worth Rs 4,034.34 crore had been placed which was about 35 per cent of the total estimated costs of plant and equipments.

The total cost of the project is Rs 22,420 crore with the first phase investment pegged at Rs 13,000 crore. The project has already attained financial closure and will have a 60:40 debt-equity ratio. While the debt component will be Rs 8,958 crore, the equity is Rs 13,452 crore.

…  While the company requires 5,279 acres for the steel plant, about 3000 acres have been acquired so far. The acquisition of additional 707 acres of private land is likely to be over by the end of this month.