Following is an excerpt from a report in Business Standard. (Thanks to Future Berhampur for the pointer.)

… Though Tata Steel’s SEZ project was cleared by the Board of Approvals (BoA) under the Union commerce ministry, it is yet to be notified due to problems in possession of land.

“The land possession problems in Chamakahandi and Basanaputi villages will be sorted out very soon. Company authorities have agreed to undertake a fresh survey on the lands being left out in these villages, for the payment of compensation and taking physical possession”, said an official of Tata Steel.

Tata Steel had initially planned for establishment of a shore-based mega steel plant near Gopalpur and applied for about 3,700 acres of land . …

Meanwhile, the company expects to take physical possession of land for the Gopalpur SEZ very soon. “We have already deposited the amount for the land acquisition and hope to get physical possession very soon for construction of the boundary walls”, said S S Routray, senior manager (administration), Gopalpur SEZ project ofTata Steel.

A tripartite meeting was held between the villagers, company officials and the district administration for physical acquisition of around 51.502 acres of land in Chamakhandi village and around 25 acres in Basanaputi village.

This meeting had a very positive response, said Routray.

… Tata Steel, on the other hand intends to withdraw from the 206.685 acres of land at Kalipalli village and 691 acres of land at Paikapada. According to official sources, though the land at Paikapada was acquired, it was not handed over to the company.

Once the implementation of the SEZ project starts, Tata Steel will have 2792.659 acres in nine villages including Chamakhandi and Basanaputi villages in its possession, sources said.