Archive for the 'Railways' Category

Kalyan Jena mentions couple of new Railway proposals and approvals: Samaja

ECOR, Khurda Rd - Balangir (under constr.), Paradip - Jatadhari - Kujanga No Comments »

They are:

  • Approval of Chakulia-Buramarra line with an estimate of 468 crores.
  • Proposal of a line via Banki for goods trains. (A line from Naraj to Banki to Khurda will form a circular Railway around greater Bhubaneswar.)

Following is an excerpt from a report in Business Standard.

Indian Railways has planned major infrastructure facilities like freight nodal points, container park and a coaching complex to cater to the proposed Petroleum, Chemical and Petrochemical Investment Region in Paradeep.

… Mr KC Jena chairman of Railway Board said that “Paradeep is poised to emerge as one of the major industrial hubs in Orissa and it is also the site for the proposed PCPIR in the state. A master plan is being prepared for the Paradeep region and according to this plan, the Railways will set up infrastructure facilities like freight nodal points, container park and a coaching complex.”

Mr Jena said that the Railways is also committed to boost connectivity in the Paradeep region which includes the 82 kilometer Paradeep to Haridaspur broad gauge line, being taken up at an investment of INR 577.78 crore. East Coast Railway has acquired 1,146 acres of private land out of the total of 1,653 acres of land required for the project. This project being implemented by Rail Vikas Nigam Limited is scheduled for completion by March 2011.

… On the 290 kilometer Khurda Road to Bolangir project, Mr Jena said that “Work is already in progress for the first 36 kilometer stretch of the project and the fund for the second phase of the project is likely to be sanctioned in this year’s railway budget.” He added that the project had suffered delay due to land acquisition problems and a fast track committee for railway projects formed under the chairmanship of the Orissa Chief Secretary was making efforts to expedite the process of land acquisition.

Mr Jena added that the overall outlay for the various railway projects in Orissa stood at INR 1,049 crore in 2008-09, compared to INR 764 crore in the previous fiscal and the sanctioned figure excludes the projects being implemented by Rail Vikas Nigam Limited.

MOU signed with Navayuga group for a port in Astaranga

Astaranga, Puri (Navayuga interested), Puri, Railways 1 Comment »

Following is an excerpt from a report in Pioneer.

… the CVR Navayuga Group on Monday inked an MoU sign with the State Government to develop a Greenfield port at Astaranga in Puri at a investment of Rs 6,000 crore. Astaranga is one of the 13 sites identified by the State Government for development of minor ports in the State.

… Chief Minister Naveen Patnaik said Navayuga Engineering had plans to invest Rs 1,500 crore in Phase 1 at Astaranga with a capacity of to move 25 million tones of cargo. "With the completion of the Phase -II and Phase-III, the total investment made at the location will be Rs 6,000 crore with a capacity of 60 million tonne," he said, adding that the project was estimated to yield revenue of Rs 20 crore per annum for Government during Phase-1 and Rs 1,000 crore per annum by the completion of Phase -III.

The project in its entirety shall be implemented over a period of eight years with Phase-1 being completed within 48 months. 10, 000 jobs will be created. The scope of the project also includes construction of a 50-km rail link to connect Astaranga with mainline at Khurda via Sakhigopal.

A report in Hindu has some more details. Following are excerpts.

The Hyderabad-based Navayuga Engineering Company has entered into a memorandum of understanding (MoU) with the Government of Orissa for the development of a modern deep water, all-weather, alongside-berthing, mechanised port at the Astaranga area located in Puri district, according to a company release. 

The MoU was entered on a build, own, operate, share and transfer (BOOST) basis. …

The first phase was planned to be made operational in four years. As per the concession agreement, all investment for the project should be arranged by the developer; the revenue share to the Government was fixed at five per cent for the first five years, eight per cent for sixth to 10th year, 10 per cent for 11th to 15th year and 12 per cent for the remaining period of 15 years.

The MoU had a provision of 30 years concession period and could be extended by an additional 20 years. The detailed concession agreement is to be signed within six months.

Kharabela Swain, MP from Orissa, has the guts to point out Lalu Yadav’s partiality

Orissa MPs, Railway network in Orissa, Railways No Comments »

Following is an excerpt from a the Lok Sabha transcript of 20th October 2008.

SHRI KHARABELA SWAIN (BALASORE): What he has done? He has taken one railway factory to his constituency, another factory to his wife’s constituency, and the third one to the UPA Chairperson’s constituency. … (Interruptions) We are nowhere.  Shall we be eligible to get any rail factory any time in life? … (Interruptions) People say that now-a-days jobs are being given in the Railways by taking land from them. … (Interruptions)

MR. CHAIRMAN: Please go to your seat. Let the Minister reply. I will give him time.

… (Interruptions)

SHRI KHARABELA SWAIN (BALASORE): Even now the Ministers in the Government are becoming Ministers by giving land in this country. … (Interruptions)

1707 hours

(At this stage, Shri Ram Kripal Yadav and some other hon. Members

 came and stood near the Table.)

… (Interruptions)

MR. CHAIRMAN: If you do not go, I have no other way but to adjourn the House. If you want me to adjourn the House, then I will adjourn it.

… (Interruptions)

SHRI KHARABELA SWAIN (BALASORE): It is because of this only. … (Interruptions) This is happening and nothing else. I strongly object to what is being done by the Railways. … (Interruptions)

MR. CHAIRMAN: Please go to your seats. If you do not go, I have no other way but to adjourn the House.

          The House stands adjourned to meet tomorrow, the 21st October, 2008 at 11 a.m.

One wonder if Lalu Yadav is the Minister of Railways for India or the Minister of Railways for UPA or the Minister of Railways for Bihar?

Open letter to the Prime Minister

APPEAL to readers, Angul, Balangir, Bouda, Gajapati, KBK Plus district cluster, Kalahandi, Kandhamala, Khordha, Khurda Rd - Balangir (under constr.), Koraput, Lanjigarh Rd - Junagarh, Malkangiri, Nabarangpur, Nayagarha, Sambalpur, Talcher - Bimlagarh (under constr.) 7 Comments »

"Dr. Manmohan Singh" <pmosb@pmo.nic.in>, "Chief Minister" <cmo@ori.nic.in>, "Orissa Governor" <govori@ori.nic.in>,
<abhijit.sen@yojana.nic.in>, <anwarul.hoda@yojana.nic.in>, <b.mungekar@yojana.nic.in>, <dch@yojana.nic.in>, <kirit.parikh@yojana.nic.in>, <mvraja@yojana.nic.in>, <plancom@nic.in>, <s.hameed@yojana.nic.in>, <vl.chopra@yojana.nic.in>, <yugandhar.bn@nic.in>, "subas@nic.in" <subas@nic.in>

cc to journalists: <abcxy123@hotmail.com>, <admin@dailypratap.com>, <akb@businessstandard.com>, <alokmehta7@hotmail.com>, <ankur@jaintv.com>, <arindam.sengupta@timesgroup.com>, <colpnk@hotmail.com>, <dr.jain@jaintv.com>, <editet@timesgroup.com>, <editor@deccanmail.com>, <editor@the-week.com>, <feedback@tehelka.com>, <ie.pksahoo@gmail.com>, <indinon@vsnl.in>, <karanthapar@itvindia.net>, <klnandan@yahoo.com>, <letters@deccanherald.co.in>, <letters@tribuneindia.com>, <lngoel@zeenetwork.com>, <mashriq@vsnl.net>, <mnutan@hotmail.com>, <mythilib@gmail.com>, <npnawani@indiatimes.com>, <nsuri@milap.com>, <pjoshi@hindustantimes.com>, <prabhu@intoday.com>, <punit.jain@timesgroup.com>, <punjabidigest@hotmail.com>, <pvohra@hindustantimes.com>, <rajc@intoday.com>, <ratnam@intoday.com>, <saeednaqvi@hotmail.com>, <sargamstudio@rediffmail.com>, <shishir.joshi@aajtak.com>, <takhatram@hotmail.com>, <tarunvijay@vsnl.com>, <thehindu@vsnl.com>, <toieditorial@timesgroup.com>, <ttedit@abpmail.com>, <vmehta@outlookindia.com>, <vsanghvi@hindustantimes.com>, "braja k mishra" <brajakmishra@gmail.com>, "manorama" <maya@mitraprakashan.com>, "Prasanta Kumar Sahoo" <pksahoo2002@gmail.com>, "Shishir Bhate" <shishirb@rediff.co.in>

cc to Orissa NDA mps: <ananta@sansad.nic.in>, <bmahtab@sansad.nic.in>, <deobk@sansad.nic.in>, <dharmendra@deogarhorissa.com>, <jualoram@sansad.nic.in>, <makswain@sansad.nic.in>, <mayfair@sansad.nic.in>, <pmajhi@sansad.nic.in>, <pyarimohan@yahoo.co.uk>, <pyarimohanap@sansad.nic.in>, <rknayak@sansad.nic.in>, <rn.pany@sansad.nic.in>, <surendra@sansad.nic.in>, "B J Panda" <office.bjpanda@gmail.com>, "Balbir Punj" <punjbk@gmail.com>, "jual oram" <jualoram@hotmail.com>, "Tathagata Satpathy" <tatzaudi@yahoo.com>

cc to Orissa opposition biggies: "janardan pati" <j_pati_orissa@yahoo.com>, "rohit pujari" <rohit_pujari2001@yahoo.com>, "Srikant Jena" <srikant_jena@hotmail.com>, "Chandrasekhar Sahu’s OSD" <skpattanayak@hotmail.com>

cc to BJP bigwigs: <advanilk@sansad.nic.in>, <ananta@sansad.nic.in>, <asahu@nic.in>, <ashourie@sansad.nic.in>, <bjpco@bjp.org>, <bjpco@del3.vsnl.net.in>, <bpapte@vsnl.com>, <chandan.mitra@sansad.nic.in>, <covdnhrc@nic.in>, <deobk@sansad.nic.in>, <gandhim@sansad.nic.in>, <george@sansad.nic.in>, <iisatwal@hotmail.com>, <jaswant@sansad.nic.in>, <jualoram@sansad.nic.in>, <kjana@sansad.nic.in>, <makswain@sansad.nic.in>, <minister@mit.gov.in>, <mnaqvi@sansad.nic.in>, <mprasad@nic.in>, <msgill@sansad.nic.in>, <murli@sansad.nic.in>, <mvnaidu@sansad.nic.in>, <najmah@sansad.nic.in>, <pati@nic.in>, <pilania.g@sansad.nic.in>, <pmajhi@sansad.nic.in>, <rajnath@sansad.nic.in>, <rn.pany@sansad.nic.in>, <spokesman_rss@yahoo.com>, <surendra@sansad.nic.in>, <swaraj@sansad.nic.in>, <vajpayee@sansad.nic.in>, <ysinha@sansad.nic.in>

cc to UPA bigwigs: <10janpath@vsnl.net>, <ambika_aicc@yahoo.com>, <arjuns@sansad.nic.in>, <chavanprithviraj@sansad.nic.in>, <cpim@vsnl.com>, <jairam@vsnl.com>, <kapilsibal@hotmail.com>, <km.sahni@nic.in>, <nath@sansad.nic.in>, <oscar@sansad.nic.in>, <praful@sansad.nic.in>, <sjaipal@sansad.nic.in>, <speakerloksabha@sansad.nic.in>, <svpatil@sansad.nic.in>, "Dr. Manmohan Singh" <pmosb@pmo.nic.in>, "Jairam Ramesh" <jairam@sansad.nic.in>, "Kamal Nath" <cim@nic.in>, "Ram Vilas Paswan" <psmin.cpc@sb.nic.in>

 FAX: PMO at 23016857 , 23015603 (Delhi STD code is 11), CMO at 674 2590 833 (home) 674 2535 100 (office) and Planning Commission at 23096699


 

To:

Dr. Manmohan Singh

Prime Minister of India

Cc: Mr. Naveen Patniak, Chief Minister of Orissa

Cc: Shri Muralidhar Chandrakant Bhandare, Governor of Orissa

 
Subject: Solving the greater Kandhamala problem – going after the root cause in a war footing

 

Dear Dr. Singh: 

While the civil society in Orissa, the nation and the world is disturbed by the  communal violence in Kandhamala, I would urge you to take steps to eradicate the root cause of the violence in Kandhamala and the nearby tribal, hilly, forested, awfully connected, poor and backward districts of Orissa (and its neighboring states). In this regard, please note that the violence did not spread to the major towns and cities of Orissa (such as Bhubaneswar, Puri, Cuttack, Rourkela, Sambalpur, Berhampur, Balasore etc.)  that are well connected (by Rail and roads), decently developed and have a civil society. 

While the violence involving the murder of Swami Laxmanananda on August 23rd 2008 and the subsequent communal violence that has taken about 40 lives is most deplorable and is in the forefront of the media, please also recall the following events that also took place within the last year in these areas:

 

  1. February 15 2008:  400 to 500 armed Naxals raided the Nayagarh armory and killed 15 people including 13 policemen.
  2. June 29 2008: 30 elite anti-insurgency policemen were killed by Maoists near Malkangiri.
  3. July 16 2008:  21 Orissa policemen were killed in a land mine explosion and firing by the ultras in Malkangiri.
  4. Dec 27 2007: Eleven churches were ransacked and torched in several areas of Kandhamal district.

Please note that these events happened in places in Orissa (Nayagarh, Malkangiri and Kandhamal) that are badly connected, near or within forests, have a large tribal population, and are among the most backward districts of India. The following map shows these districts are surrounded by large tracts of dense and open forested areas, and partly explains why the naxalites and Maoists are able to make them their base and why it has been difficult to deploy adequate police there in a timely manner.

(NOTE: Phulbani is now called Kandhamala)

(Note: The lines in red are the ones that are needed to bring rail connectivity to the Kandhamala, Nayagarh and Malkangiri districts and criss-cross the big connectivity gap in the heart of Orissa. The crossed segments are already approved but progressing very slowly.)

 

Sir: As an economist and a world leader you must know that lack of connectivity, lack of development, lack of a civil society, entrenched forest and mountainous areas together with a different population base is a recipe for the sprouting of troubled areas. This is true all across the world; from J& K and North eastern areas of India to caucuses in Asia. While one cannot and should not get rid of the mountains or the people, the problem can be solved by making the areas well connected and bringing development. The Indian government is doing that in J & K and in the northeast; but has mostly forgotten about the similar areas in Orissa, Chhatisgrah, and Andhra Pradesh, which are the favorite bases of the Naxals and Maoists.

Sir: We would like you to pay the same attention to these areas in terms of connectivity, development, and creation of civil societies, as you do to the North east and J & K. In particular we would request that following be done in a war footing during the 11th plan.

(i)                  The Vijaywada-Ranchi highway that passes through many of these areas be completed.

(ii)                Broadband connectivity be brought to these districts with adequate access locations.

(iii)                Two Railway lines, parts of which have already been sanctioned by the Railways but are progressing slowly, are completed and made operational. Those lines are:

a.       Khurda Rd – Balangir (passes through Nayagarh and Boudh) – This line was sanctioned in 1994-95 is progressing very slowly.

b.      Bhadrachalam Rd (Andhra Pradesh) – Malkangiri – Jeypore – Nabarangpur – Junagarh – Lanjigarh Rdpassing through Kandhamala – Boudh – Angul – Talcher – Bimlagarh: Several segments of these lines are approved but progressing slowly. Those segments are Junagarh – Lanjigarh Rd and Talcher – Bimlagarh. Angul – Talcher is operational.

(iv)              With the above lines operational, development should be brought into Kandhamal, Boudh, Gajapati, and KBK districts (including Kalahandi and Malkangiri) through 1-2 Rail factories and public sector units that can use the steel and aluminum and power produced in abundance in Orissa.

(v)                Orissa govt. should be encouraged and aided to establish a university in Kandhamala and another in Kalahandi.

(vi)              A branch of the Indira Gandhi National Tribal University be established in one of these districts.

(vii)             Orissa govt. should be encouraged and aided to establish a government medical college and nursing college in Kandhamala or Boudha district.

Sir:  In regards to the cost of establishing the Railway lines, please note that as per the calculation in  http://kbkrail.orissalinks.com/ Indian Railways is scheduled to make a profit of 2679.72 crores/year from its operations in Orissa. If 1500 crores of this money (the rest may go to Indian Railway’s current plans for Orissa) is put into Orissa, in just 2-3 years the above mentioned lines could be completed.

Sir: We sincerely hope that you will translate the great concern you have shown towards the recent violent events to the above mentioned action items that address the key issues of lack of connectivity and development in these areas and thus provide a long term and real solution.

Sincerely

 

Appendix:

1. Estimated profit Indian Railways will make from Orissa in 2008-09:

Zone in Orissa

Total Route Kms

Route kms in Orissa

Estimated

2008-2009 profit (in crores)

Orissa’s proportional share of the profit in 2008-2009

ECOR

2430

1607

3077.15

(next page)

2034.97 crores

SECR

1599

51

2529.89

(next page)

80.69 crores

SER

2577

589

2467.88

(next page)

564.06 crores

Total

 

2247

 

2679.72 crores

 

2.  One of the earlier planning commissions has noted in http://planningcommission.nic.in/plans/stateplan/sdr_orissa/sdr_orich2.doc

“Railways have always played an important role in economic development and rapid social transformation in all parts of the globe. It is one of the key economic infrastructures. However, it is most unfortunate that in a poor and backward state like Orissa, development of rail networks has received much less attention of the Central Government in the post-independence period. There are as many as seven districts like Boudh, Kandhamal, Deogarh, Nayagarh, Kendrapara, Malkangiri and Nabarangpur out of the 30 districts of the state, which do not have any railway line passing through them. In the year 1998-99, the density of railway route length per 1000 sq. km of area in Orissa was only 15.03 km as against 42.66 km in West Bengal and 19.11 km. at all-India level”.


3. The tribal population percentage of the KBK districts are as follows:  Malkangiri  58.36% ST  (+19.96% SC),  Rayagada 56.04% ST  (+14.28% SC),  Nabarangpur 55.27% ST (+15.09% SC), Koraput 50.67% ST (+13.41% SC), Nuapada 35.95%  ST(+13.09% SC), Kalahandi 28.88% ST (+17.01% SC), Sonepur 22.11% ST (+9.5% SC), Balangir 22.06% ST (+15.39% SC). Two adjacent districts also have high tribal population. They are Kandhamala 51.51% ST (+18.21% SC) and Gajapati 47.88%  ST(+8.77% SC). 

 

4. The literacy rates in the KBK districts are abysmally low. Malkangiri 31.26%, Nabarangpur 34.26%, Rayagada 35.61%, Koraput 36.2%, Nuapada 42.29%, Kalahandi 46.2%, Balangir 54.93%, Sonepur 64.07%. Two adjacent districts also have low literacy: Gajapati 41.73% and Kandhamala 52.95%. The state average is 63.1%.

5. Population below the poverty line in southern Orissa (of which KBK is a part) is reported to be 89.17% of the people according to the 1999-2000 NSS data and 72% of the families according to the 1997 census.

Naupada-Gunpur railway line to be ready by March 2009: Dhartri

Gajapati, Naupada - Gunupur (Gauge conversion), Rayagada No Comments »

New lines under construction and under survey in ECOR

ECOR, SER 1 Comment »

New lines: http://eastcoastrailway.gov.in/common/department-division-info/construction/new-lines.htm

   Daitari - Banspani (155 Km.)
   Koraput - Rayagada (164 Km.)
   Khurda - Bolangir (289 Km.)
   Talcher - Sambalpur (174.112 Km.)
   Langigarh Rd. - Junagarh (56 Km.)
   Haridaspur - Paradeep (82 Km.)
   Sukinda Road - Angul (98 Km.)
   Talcher - Bimalgarh (154 Km.)

New lines under survey: http://eastcoastrailway.gov.in/common/department-division-info/construction/new-lines-under-survey.htm

Jeypore-Kottameta new BG rail link 128 Orissa
Puri-Konark new BG rail link 30 Orissa
Phulbani-Berhampur new BG line 175 Orissa
Talcher/Hindol Road -Gopalpur/Berhampur new BG rail link 245 Orissa
Talcher-Bimlagarh new BG rail link 130 Orissa
Bargarh-Nawapara Road new BG link via Padampur 120 Orissa
Jeypore-Nawarangpur new BG line 45 Orissa

 

 

Calculating Indian Railways’ estimated profit from Orissa in 2008-09

APPEAL to readers, Railway network in Orissa, SECR, SER No Comments »
  Total Route kms Route Kms in Orissa

Total estimated Profit in 08-09 (in crores)

Orissa’s portion of the profit (in crores)
ECOR 2430 1607 3077.15 2034.97
SECR 1599 51 2529.89 80.69
SER 2577 589 2467.88 564.06
    2247   2679.72

 

Indian Railways exploitation of backward and tribal areas of Orissa: confronting Railway Board Chair with the facts in Toronto

Balasore - Niligiri (defunct?), Baripada - Bangiriposi (under constr.), Closure notice once issued, ENVIRONMENT, EXPOSING ANTI-ORISSA-GROWTH SCHEMES, FINANCE & BANKING, Gajapati, Ganjam, Interstate disputes on Water and rivers, Jaroli - Deojhar .. Chaibasa, KBK Plus district cluster, Kandhamala, Keonjhar, Koraput - Rayagada, Mayurbhanj, Nayagarha, Orissa Consumer Welfare Foundation, Paradip - Jatadhari - Kujanga, Railway maps, Rajathagara - Nergundi, Rayagada, Samaja (in Oriya), Sambalpur, Sonepur, Sundergarh, Talcher - Barang, Titlagarh - Jharsugurha Jn, Tomka - Jaroli, Uncategorized 3 Comments »

Following is the news report on the discussion (almost a confrontation) with the Railway Board Chair, as reported in India Abroad. The basic premise behind our grievances against Indian Railways and our demands is simple.

  • Indian railways is scheduled to make 2500-3000 crores/year from Orissa, but spends only 1000 crores/year on Orissa in terms of new lines, doubling and gauge conversion.
  • Its current plan for major spending includes freight corridors, metro rails, and high speed rails, none of which touch Orissa. It plans to do gauge conversion of 12000 kms, most of which is unprofitable (this proves that Indian Railway lies when it says it only does profitable lines), very little (less than 100 km) of which is in Orissa.
  • Orissa is already behind the national average in terms of rail density and way behind its neighbors such as West Bengal and Bihar. If no changes are made to the 11th plan IR allocations Orissa will further fall behind.
  • Indian Railways must not take money from its profit in Orissa, and spend it else where, until it takes care of proper connectivity to Orissa’s tribal, backward and maoist infested areas. The 2500-3000 times 5 = 12,500 -15,000 crore that Indian Railways will profit from Orissa during the 11th plan must be spend in new lines in Orissa until the (i)-(v) lines below and other port and mine connectivity lines are completed during the 11th plan.
  • To Mr. Jena’s retort that Mumbai earns so much in taxes and not all of it is spent in Mumbai; we reply that it is often acceptable to take from rich and give to poor; But when did it become acceptable to take from poor (Orissa) and give to rich (freight corridors etc. in other states)?

The lines in Orissa connecting to the tribal and backward areas that we demand to be finished during the 11th plan are:

  • (i) Khurda Rd - Nayagarh - Balangir: Lack of connectivity was one of the reasons a recent Maoist mayhem happened in Nayagarh. It seems after recent events, including the confrontation with the Railway Board Chair and various dharanas in Bhubaneswar, IR has started responding to this demand, but not to the extent to promise its completion during the 11th plan. Note that Balangir is the B in the KBK districts that are the most backward in India.
  • (ii) Lanjigarh Rd - Junagarh - Nabarangpur - Jeypore - Malkangiri - Bhadrachalam Rd in Andhra Pradesh: Only small part of this is approved. Most of it is not even surveyed. In the long run this will really bring those parts of Orissa closer to the rest of Orissa. This is the most important connection and has to be take care of at the earliest. Like the approved Vijaywada-Ranchi highway, this line will create an alternative Hyderabad - Ranchi path passing through backward and tribal areas of Andhra Pradesh, Orissa and Jharkhand. This line will connect the Kalahandi and Koraput districts, the two K’s in KBK. The recent Maoist attack and killing of the Greyhound forces in Malkangiri might have been prevented if this line existed as then the forces would have used the train rather than being seating ducks taking a boat across a lake in Malkangiri.
  • (iii a) Rayagada - Gopalpur: This has been surveyed and but work on it has not started. Note that Rayagada is part of the undivided Koraput district, one of the K’s of KBK. This line could come under port connectivity and will be a viable line connecting the industries near Rayagada with the upcoming port in Gopalpur.
  • (iii b) Gunupur - Theruvali: This will add to the Naupada-Gunupur line and make it an economically viable line. (IR and Mr. Jena agree about its importance.) This line will be completely inside the Raygada district, part of the undivided Koraput district, one of the K’s of KBK.
  • (iv) Talcher - Bimlagarh (connectivity to the tribal district of Sundergarh): This line has been approved but is only being given a few crores each year, which is less than the inflation. This line will reduce the distance between Sundergarh district and teh coastal areas significantly. For example, it will make Rourkela only 4-5 hrs from Bhubaneswar.
  • (v) Baripada/Buramara - Chakulia: This line will connect the tribal district of Mayurbhanj to tribal areas of Jharkhand. It will add to the Rupsa-Baripada-Bangiriposi line and make it an economically viable line. (IR and Mr. Jena agree about its importance.)

All these lines can be completed if Indian railways just suspends its practice of taking from poor (Orissa) and giving to the rich for only a few years (may be just 3-4 years). The following maps show the above mentioned lines.

CM pursues various rail projects in Delhi

Chief Minister's actions, Railways No Comments »

Following is from http://rc.orissa.gov.in/index3.asp?linkid=30&sublinkid=593.

Shri Naveen Patnaik, Chief Minister, Orissa had a meeting with Shri K.C.Jena, Chairman, Railway Board today and emphasized the need for expansion and augmentation of railway infrastructure in the State of Orissa as it is on the threshold of a major industrial upsurge. This will necessitate laying of new rail links, construction of elaborate rail terminals and bulk cargo handling points. He pointed out that the railway route length in Orissa is well below the national average and also much less than the neighbouring States like Andhra Pradesh, West Bengal and Bihar.

The CM mentioned that there has been very little progress of Khurda Road-Bolangir railway line and the Ministry of Railways have allocated only Rs.32 crores during 2008-09 and stressed for increased allocation.

The CM has drawn the attention of the Chairman to the KBK districts which have a high percentage of tribal population and stressed the need for sanction of Jeypore-Malkanglri (117 Kms) line for which survey has already been completed. He further stated that advent of railways would lead to socio-economic development in that region.

He also informed that the Government of Orissa has entered into MOUs for setting up two alumina plants in the region and in this context, Lanjigarh Road-Junagarh new B.G. rail link assumes significance. He desired that the section between Lanjigarh and Bhawanipatna should be commissioned early.

He has also reiterated Government of Orissa’s interest for development of Gopalpur, Dhamra and Subarnarekha mouth (Kirtania) ports into all weather ports along its coast line and stressed that railway lines connecting Rupsa-Burhamara to Chakulia (50 kms), Nuapada-Gunupur B.G. Rail link to Theruvali (79 kms) and Banspani-Barbil for which preliminary surveys have been completed assume critical importance for movement of in bound and out bound traffic likely to be generated by the coastal ports, industries as well as mines in the hinterland

He underlined the need for expeditiously completing the residual work on Daitari-Banspani B.G.Rail Link and to introduce an intercity express between Bhubaneswar-Jamshedpur via Keonjhar. He also desired early commissioning of Cuttack-Barang doubling. The Chairman, Railway Board assured Hon�ble C.M. that Puri-Keonjhargarh Coaching Train services will be introduced before October, 2008.

Since the lack of adequate rail infrastructure has hindered the socio-economic growth of the State, he impressed upon the need to consider increased allocation of funds to ensure speedy execution of the sanctioned projects and also sanctioning of the new projects, surveys. He expressed happiness for identifying Bhubaneswar as one of the locations for construction of a world class railway station.

He also emphasized the need for introduction of new trains, extension and increase in frequency of mail/express trains, improved passenger amenities at stations etc to meet the aspirations of the people of Orissa and the developmental needs of a fast growing economy. He pointed out that although four new trains and one extension were announced in the Railway Budget of 2008-09, they have not yet been introduced and requested for early introduction of these trains.

The CM also desired early normalization of Balasore-Kharagpur section and restoration of normal coaching services as nineteen trains still stand cancelled because of the breach of railway track between Contai Road and Bakhrabad due to the recent floods.

The Chairman, Railway Board assured the Hon’ble C.M. to expedite all the above Projects of Railways in Orissa

The Chief minister’s requests were reasonable as it was made to the Railway Board chair who can only do things within the set parameters. The CM needs to go to the planning commission and the PM to make a broader request of complete connectivity to KBK+ and other adivasi districts within five years. The important parts he missed emphasizing are:

  • Junagarh - Nabarangpur - Jeypore; Malkangiri - Bhadrachalam - Bhadrachalam Rd
  • Talcher - Bimlagarh

Update on World Class station in Bhubaneswar

Bhubaneswar- Cuttack- Puri, Railways No Comments »

Following are excerpts from a report in the Economic Times.

A 12-member Chinese team will arrive here on July 12 on a week-long visit to inspect the railway stations at Bhubaneswar and Byppanahalli in Bangalore.

The countries had signed a Memorandum-of-Understanding (MoU) in this regard on January 14 during Prime Minister Manmohan Singh’s visit to Beijing. The agreement, valid for three years, envisages development of rail-related programmes of mutual interest.

The high-level delegation headed by Wu Wei, Director of Sino-India Railway Cooperation Working Group, will be assisted by RITES, which will provide details required for the work.

However, a senior official of the Railways Ministry said a preliminary assessment has revealed that the land available at Bhubaneswar railway station is inadequate for the project.

In that case, a nearby station at Baranga may be chosen for development into a world class station, he said, adding a final decision will be taken only after consultations with the Chinese team.

“After visiting these places, the team will share their views with us about the way to go ahead with the project.”

ECOR and SER Timetable changes relevant to Orissa

ECOR, Railway Budget 2008, SER No Comments »

Several new trains, extensions, and frequency increases relevant to Orissa were announced in the 2008-09 Railway budget and the subsequent debate in the parliament. Details about their timings and the route they will take will appear in the Time Table that is usually published on July 1st. Few days prior to that the major changes are released. Following are three such releases.

From http://eastcoastrailway.gov.in/custom/press_release/index.php.

Ministry of Railways has decided to introduce eight new trains, extension of two trains, increase in frequency of two trains, speed up of seven trains and timings change for seven trains in ECoR jurisdiction in the New Time Table being implemented from 1st July’08:

NEW TRAINS

Two daily new trains, three weekly new trains, two bi-weekly new trains and one tri-weekly trains will be introduced in ECoR jurisdiction in the new Time Table. Introduction of these trains will be notified later.

One new bi-weekly Garib Rath Super Fast Express train will be introduced between Puri and Howrah. 2882 Puri-Howrah Garib Rath Super Fast Express train will leave Puri at 10.00p.m on every Monday and Wednesday and will arrive Howrah at 07.05a.m on the next days. Similarly, in the return direction, 2881 Howrah-Puri Garib Rath Super Fast Express will leave Howrah at 08.55p.m on every Tuesday and Thursday and will arrive Puri at 05.50a.m on the following days.

One new bi-weekly Super Fast Express train will be introduced between Bhubaneswar and Lokmanya Tilak Terminus (LTT). 2880 Bhubaneswar - LTT Super Fast Express train will leave Bhubaneswar at 07.20a.m on every Monday and Thursday and will arrive LTT at 01.35p.m on the next days. Similarly, in the return direction, 2879 LTT-Bhubaneswar Super Fast Express will leave LTT at 00.15a.m on every Wednesday & Saturday (Midnight of Tuesday & Friday) and will arrive Bhubaneswar at 07.10a.m on the next days.

One new weekly Express train will be introduced between Puri and Darbhanga. 8419 Puri-Darbhanga Express train will leave Puri at 02.10p.m on every Thursday and will arrive Darbhanga at 11.05a.m on the next days. Similarly, in the return direction, 8420 Darbhanga-Puri Express will leave Darbhanga at 07.15a.m on every Saturday and will arrive Puri at 03.30a.m on the following days.

One new weekly Express train will be introduced between Bhagalpur and Yeshvantpur via Bhubaneswar. 2254 Bhagalpur-Yeshvantpur Super Fast Express train will leave Bhagalpur at 01.30p.m on every Wednesday and will arrive Yeshvantpur at 09.15a.m on the next 2nd days. Similarly, in the return direction, 2253 Yeshvantpur-Bhagalpur Super Fast Express will leave Yeshvantpur at 12.45p.m on every Saturday and will arrive Bhagalpur at 08.30p.m on the 2nd next day.

Another new weekly Express train will be introduced between New Dibrugarh Town and Yeshvantpur via Bhubaneswar. 5902 New Dibrugarh-Yeshvantpur Express train will leave New Dibrugarh at 06.45p.m on every Friday and will arrive Yeshvantpur at 12.10p.m on the next 2nd days. Similarly, in the return direction, 5901 Yeshvantpur-New Dibrugarh Express will leave Yeshvantpur at 11.55p.m on every Monday and will arrive New Dibrugarh at 08.00p.m on the 2nd next day.

One new daily Express train will be introduced between Puri and Keonjhargarh. 8416 Puri-Keonjhargarh Express train will leave Puri at 05.25a.m regularly and will arrive Keonjhargarh at 12.00 noon on the same day. Similarly, in the return direction, 8415 Keonjhargarh-Puri Express will leave Keonjhargarh at 01.00p.m and will arrive Puri at 08.30p.m.

Another new daily Express train will be introduced between Bhubaneswar and Paradeep. 8414 Bhubaneswar-Paradeep Express train will leave Bhubaneswar at 07.05a.m regularly and will arrive Paradeep at 09.45a.m. Similarly, in the return direction, 8413 Paradeep-Puri Express will leave Paradeep at 06.00p.m and will arrive Bhubaneswar at 09.10p.m.

EXTENSION:

Two bi-weekly express trains i.e. Nizamabad-Secunderabad bi-weekly and Varanasi-Ranchi bi-weekly will be extended to Sambalpur in the New Railway Time Table which will be notified later.

INCREASE IN FREQUENCY

The frequency of Bhubaneswar-Baripada-Bhubaneswar tri-weekly superfast express has been decided to increase the frequency to six days in a week from 30th June 2008. 2892 Bhubaneswar-Baripada Superfast Express will run daily w.e.f. 30th June 2008 except Saturdays from Bhubaneswar. Similarly, in the return direction, 2891 Baripada-Bhubaneswar Superfast Express will run daily w.e.f 1st July 2008 except Sundays from Baripada.

The frequency of Bhubaneswar-New Delhi-Bhubaneswar bi-weekly Rajdhani express has been decided to run as tri-weekly in the new Time Table which will notify later. 2421 Bhubaneswar-New Delhi Rajdhani Express will run on every Sunday, Wednesday and Saturday. Similarly, in the return direction, 2422New Delhi-Bhubaneswar Rajdhani Express will run on every Sunday, Monday and Friday in the new time table.

SPEED UP AND CHANGE IN TIMINGS

Seven trains have been speeded up in the new time-table including the timings of 14 trains at different stations have been changed. Bhubaneswar-Visakhapatnam Intercity Express, Bhubaneswar-Howrah Jan Shatabdi Express, Okha-Puri Express, Sambalpur-Puri Intercity Express , Raipur-Bhubaneswar Express, New Delhi-Puri Neelachal Express and Pondicherry-Bhubaneswar Express have been speeded up from 5 minutes to one hour 50 minutes from 1st July.

8411 Bhubaneswar-Visakhapatnam Intercity Express will leave Bhubaneswar at 6.45a.m instead of 5.25a.m and will arrive Visakhapatnam at 02.35p.m instead of 02.10p.m. The timings for this train at other stations have also been changed.

8412 Visakhapatnam-Bhubaneswar Intercity Express will leave Visakhapatnam at 02.55 p.m. instead of 02.35 p.m. and will arrive Bhubaneswar at 11.20 p.m. instead of 10.55 p.m.

2801 Puri-New Delhi Purusottam Express will leave Puri at 09.45p.m instead of 10.00p.m and will arrive New Delhi at 05.05a.m instead of 04.55 a.m.

2896/2888 Puri-Howrah Weekly Express trains will leave Puri at 10.00p.m instead of earlier 09.45 p.m. and will arrive Howrah at 07.05a.m instead of 06.45 a.m.

2892 Bhubaneswar-Baripada Express will leave Bhubaneswar at 05.10p.m instead of 05.30p.m and will arrive Baripada at 10.10p.m instead of 10.30 p.m.

8304 Puri-Sambalpur Intercity Express will leave Puri at 03.45p.m instead of 04.30 p.m. and will arrive Sambalpur at 10.10 p.m. instead of 10.45 p.m.

8463 Bhubaneswar-Bangalore Prashanti Express will leave Bhubaneswar at 05.45 a.m. instead of 04.15 a.m. and will arrive Bangalore at 11.30a.m instead of 10.00 a.m.

222 Puri-Angul Passenger will leave Puri at 04.00 p.m. instead of 03.30 p.m. and will arrive Angul at 09.15 p.m. instead of 08.30 p.m.

2074 Bhubaneswar-Howrah Jana Shatabdi Express will leave Bhubaneswar at 06.20 a.m. instead of 06.00 a.m. and will arrive Howrah at 12.50 p.m.

8402 Okha-Puri Express leaving Okha at 07.15 a.m. will arrive Puri at 10.50 a.m. instead of 12.40 p.m.

8303 Sambalpur-Puri Intercity Express will leave Sambalpur at 06.10 a.m. instead of 06.15 a.m. and will arrive Puri at 12.45 p.m. instead of 01.30 p.m.

8426 Raipur –Bhubaneswar Express will leave Raipur at 05.15 p.m. instead of 05.00 p.m. and will arrive Bhubaneswar at 07.35 a.m. instead of 07.45 a.m.

2816 New Delhi –Puri Neelachal Express leaving New Delhi at 06.30 a.m. will arrive Puri at 12.10 p.m. instead of 01.15 p.m.

2897 Pondicherry –Bhubaneswar Express leaving Pondicherry at 06.15 p.m. will arrive Bhubaneswar at 06.40 p.m. instead of 07.25 p.m.

The timings for many of these above trains at different stations have also been changed. Passengers are requested to enquire about the change of timings of the trains at different nearest stations to avoid inconvenience. Railway sources have also advised all concerned to dial “139″ to know all details about new train services. This BSNL numbered can be dialed from any land line, GSM or CDMA connections.

From http://www.serailway.gov.in/hq/pro/default.htm.

  • One pair of Bi-weekly Super Fast Garib Rath Express [2881/2882] between Howrah-Puri-Howrah
  • One pair of Weekly Express [2254/2253] between Bhagalpur-Yesvantpur-Bhagalpur via Howrah and Kharagpur.
  • One pair of Weekly Express [5902/5901] between New Dibrugarh Town-Yesvantpur via Howrah and Kharagpur.
  • One pair of Bi-weekly Super Fast Express [2880/2879] between Bhubaneswar-LTT via Jharsuguda.
  • One pair of Weekly Express [8419/8420] between Puri-Darbhanga via Kharagpur- Asansol.
  • 8611/8612 Ranchi-Varanasi Express will be extended to run from Sambalpur twice a week with new number 8311/8312 as Sambalpur-Ranchi- Varanasi Express.
  • 2021/2022 Howrah-Barbil Janshatabdi Express from existing six days a week to daily service with effect from 1st. July, 2008.
  • 2421/2422 Bhubaneswar-New Delhi Rajdhani Express via Kharagpur and Adra from existing bi-weekly to tri-weekly.
  • 2891/2892 Baripada-Bhubaneswar Express from existing tri-weekly to six days a week w.e.f. 1st. July, 2008 ex. Baripada.
  • 2831/2832 Ranchi-Bhubaneswar Garib Rath Express will originate/terminate from/to Hatia instead of Ranchi with effect from 19th. August, 2008.

From the South Central railway ad:

  • The biweekly Nizamabad-Visakhapatnam (8309/8310) express will be extended to Sambalpur. It will leave Sambalpur on Mondays and Fridays at 9:15 AM and reach Secunderabad at 8:20 AM and Nizamabad at 11:50 the next morning. It will leave Nizamabad at 18:35 on Tuesdays and Saturdays, leave Secunderabad at 21:45 and then reach Sambalpur at 21:30 the next day.
  • Prashanthi Express timings have been changed effective July 1 to leave Bhubaneswar about 2 hours later than its original time. Earlier it used to leave Duvadda at 11:59. Now it will leave Duvadda at 13:42. It used to leave Bhubaneswar at 4:15 AM; now it will leave at 5:45 AM.

Railway Budget 2008-09: Few highlights in Odisha context

Railway Budget 2008 No Comments »

Railway budget 2008-09(PDF):

  • 75% of Railways goods traffic moves on about 20,000 km of the railways’ high density network, coal and iron ore routes and port connectivity railway lines.
  • Coal is the mainstay of Railway’s freight traffic. Loading of coal in 2007-08 is likely to be 336 MT. Most of the new dedicated routes for coal movement will be fit for 25 ton axle load trains.
  • The Railways receives 120 MT traffic from the steel industry every year.

Odisha is a major contributor to above two, coal and steel sectors, from which Indian railway makes a large share of profit and East Cost Railway is second most profit making zone of Indian railway.

However, in social responsibiltiy Railway has contributed little towards backward region development programme like for Kalhandi Balangir Koraput Kandhamal region.

  • There is no new line proposed for Odisha during this budget.
  • Based on demands, the following surveys are proposed to be taken up in Odisha:

Junagarh-Ambaguda
Barbil-Banspani
Kantabanji-Navrangpur-Jeypore
Khurda Road-Rajatgarh

Note:

(1) Survey has no meaning unless it is approved by railway. Junagarh – Nabarangpur was under consideration since years (from early 1990s, but no survey was under taken till now)

(2) Khordha road – Balangir was approved in 1993, but not yet started properly

(3) Lanjigarh road – Junagarh was approved in 1990 with initial estimate cost 250 crores, the project in not yet completetd by near about two decades.

(4) Bimalgarh – Talcher, on the ground no progress has been made since approval.

Uncetainty over construction of Talcher Bimalagarh Railway Line

Talcher - Bimlagarh (under constr.) No Comments »

Pragativadi reported that land acquisition for Talcher Bimalagarh railway line is delaying the project.

POSCO agrees to contribute towards Paradeep-Haridaspur doubling: Sambada

Haridaspur - Paradeep (under constr.), Jagatsinghpur, Jajpur, Kalinganagar- Chandikhol- Paradip, Kendrapada, POSCO, Paradip - Jatadhari - Kujanga No Comments »


Keonjhar-Puri train to start towards the end of June: Samaja

ECOR, Keonjhar, Orissa MPs, Railway Budget 2008, Samaja (in Oriya) 6 Comments »


Khurda-Balangir work stopped for now?

Khurda Rd - Balangir (under constr.), Railway network in Orissa No Comments »

Following is from Sambada:



Following is from Samaja:


Railway board Chair Kalyan Jena’s assessment of Orissa rail projects

Khurda Rd - Balangir (under constr.), Naupada - Gunupur (Gauge conversion), Puri - Konark No Comments »

Following is an excerpt from a report in Hindu.

The Indian Railways on Monday finally spelt out its plan of action to bring the Khurda-Bolangir new broad gauge line, which was sanctioned 13 years ago, back on track here.

Addressing a press conference, Chairman of Railway Board Kalyan Coomar Jena said the Orissa government had been approached to provide land required for the 290-kilometre-long stretch Khurda-Bolangir line free of cost.

Moreover, funds available in the National Rural Employment Guarantee Scheme (NREGS) with the State should be diverted to take up earthwork needed for laying the new line, Mr. Jena said.

“If the state government responds positively to our idea, the Khurda-Bolangir project would move much faster,” Mr. Jena said.

… The proposed Khurda-Bolangir line is a vital railway link, which would connect coastal Orissa with the western part. Though people had started demanding the railway link more than two decades ago, it was sanctioned in the year 1994-1995.

The projected cost of the project has now reached Rs. 1,000 crore.

The East Coast Railway (ECoR) said 52 per cent of cumulative physical progress had been achieved while work was in progress up to 36 km distance. Till March 2007, only Rs. 67.83 crore had been spent on the project.

The Indian Railways also sought the State government’s cooperation on land acquisition for the Puri-Konark railway link. 

Sharing the progress on the proposed world-class railway station at Bhubaneswar, Mr. Jena said the railway was scouting for suitable land for the project.

He said Chinese expertise had been sought to prepare concept of the station, which would require at least 200 acres of land.

Subsequently, an expression of interest would be floated inviting interested firms to execute the project.

A high-level Chinese railway delegation headed by W.U. Wei, Director of Sino-India Railway Co-operation Working Group along with 12 members had visited the city for conducting a survey for developing a world class station here.

Following is an excerpt from a report in Kalinga Times.

… Jena said the gauge conversion of 90 km Naupada-Gunupur would be completed during the current fiscal.

Wi-fi in Cuttack station

Bhubaneswar- Cuttack- Puri, ECOR, Wi-fi No Comments »

Following is an excerpt from a news report in Economic Times.

CUTTACK: Chairman of Railway Board K C Jena on Sunday inaugurated the wi-fi facility at the railway station here to enable passengers pursue their professional and personal activities even during travel.

Any passenger could access the internet at the station with the help of a wi-fi enabled laptop and use credit card of any bank for online booking, he said.

Jena said the facility, introduced for the first time in the East-Coast Railway division, would help the bonafide passengers to enjoy wireless broadband access, access to reservation system, check e-mail and surf net at platforms while travelling.

The facility, provided by M/s Railtel, was currently available in 53 stations across the country.

In the near future, Bhubaneswar, Puri and Visakhapatnam stations would get the facility, railway sources said.

Rail budget hotels in Puri and Bhubaneswar

Bhubaneswar- Cuttack- Puri, Hotels and resorts, Khordha, Puri, Railways