Following is an excerpt from a report in Economic Times.

The Orissa government has given administrative sanction for acquiring land at Patana tehsil in Kenojhar district for Arcelor-Mittal’s proposed 12 million tons per annum steel plant.

The company … has already deposited Rs 4.03 crore with the Industrial Development Corporation (IDCO) as processing fee for phase-I land acquisition.

The government has also appointed a nodal officer to oversee land acquisition process and other issues concerning the company’s greenfield project, said Steel and Mines Minister Padmanabha Behera.

Arcelor-Mittal is understood to have sought nearly 8,000 acres of land for the purpose and the state is believed to have agreed to the request.

The government has, however, cleared acquisition of only 1,224 acre of land spread over three villages like Angikala, Baradangua and Bhrungaraj under Patana tehsil in the first phase of land acquisition.

The 1,224 acres demarcated for the first phase acquisition comprised 431 acres of government land and 739 acres belonging to private owners.

While the government had fixed price per acre of state land at Rs two lakh, it was yet to decide cost of private land which would be fixed according to rehabilitation and resettlement policy.